Bid due date: May 3rd 2019 at noon, 12.00 p.m. (AST)
Project Location: Behind 96 Saunders Rd, McAdam, NB E6J 1L2 (McAdam Train Station)
Project Overview: Nature Trail Upgrade includes the repair, demolition and construction of five walking bridges, three covered shelters and two benches.
Project Details/Specifications:
a) Repair to existing (1) covered bridge (34′ x 8′) including roof replacement, replacement of sills, elevate and reinforce structural support.
b) Demolition and construction of walking bridge (42′ x 6′) including handrails.
c) Demolition and construction of walking bridge (48′ x 6′) including handrails.
d) Demolition and construction of walking bridge (48′ x 6′) including handrails.
e) Demolition and construction of walking bridge (17′ x 5′)
f) Demolition and construction of (3) covered shelters. Two (7′ x 5′) and one (8′ x 10′)
g) Demolition and construction of two wooden benches, each 5′ in length
*Note, all dimensions are approximate. For a site visit to obtain exact measurements, please contact the office.
Timeline: Work must commence no later than May 13th 2019, and be completed by June 7th 2019.
Additional requirements:
- Bridges require pressure treated lumber
- Bidder is responsible for the disposal of all construction and demolition refuse.
- Work must be compliant with building code, as prescribed by the Village of McAdam Building Inspector.
- Bidder must be in good standing with WorkSafe NB
- Quote must be broken into each specification (a-g)
Bid Instructions:
Mail or hand deliver sealed bids to:
Village of McAdam, 146 Saunders Road, McAdam, NB E6J 1L2 before May 3rd 2019 at noon, 12:00 pm (AST)
For any questions or inquiries please call CAO Ed Arsenault at 784-2293.